Ghana Gas completes planned maintenance ahead of schedule

The maintenance team of Ghana National Gas Limited Company has successfully completed scheduled maintenance works ahead of time, handing over the facility to the operational unit for normal activities to resume.
The works, which were initially expected to take 14 days as estimated by the Ministry of Energy and Green Transition, were completed in record time.
Key tasks carried out included:
Servicing of the Heat Medium System
Calibration of Safety Systems
Overhaul of the Transmission Compressor
Chief Executive Officer, Ms. Judith Adjobah Blay, commended the technical and maintenance teams for their dedication and teamwork.
She noted that their commitment and collaboration were instrumental in completing the project efficiently and ahead of schedule.
Acting General Manager of Engineering and Maintenance, Mr. Maxwell Kali, confirmed that the plant is expected to stabilise and begin receiving the expected volumes of gas within hours.
Similarly, Mr. Sampson Doe, Acting General Manager of Operations, expressed optimism about smooth operations in the coming days, following the successful completion of the maintenance exercise.
Trending News
U.S., Ghana explore stronger health collaboration
09:00E/R: Rehabilitation works begin on Koforidua-Suhum road to ease commuters’ plight
09:10President Mahama explores education and biotechnology partnerships in Singapore
06:39Ghana poised to become Africa’s digital trade hub – Vice President
16:39Don’t be intimidated by the presence of police; they're here to provide security – NYA CEO to Akwatia voters
08:50NDC’s Godwin Tameklo questions the use of Internally Generated Funds at Ridge Hospital
08:56Hassan Tampuli supports 238 tertiary students in Gushegu
06:13Volta Region launches National Apprenticeship Programme with 2,060 beneficiaries
13:51E/R: Vigil held in honour of late Ernest Yaw Kumi
10:45Razak Kojo Opoku urges NPP to resist ‘entrenchment theorists’
07:31