GAF clears over 50% of Accra–Kumasi expressway corridor ahead of construction
The Ghana Armed Forces (GAF) says it has completed more than half of the corridor-clearing works for the proposed Accra–Kumasi Expressway, bringing the flagship infrastructure project a step closer to the construction phase.
According to the latest progress update, engineers had cleared 89.5 kilometres of the designated route as of June 25, 2026, representing 50.9 per cent of the total 175.6-kilometre corridor earmarked for the expressway.
Project Coordinator and Manager, Colonel Alex Twumasi, said the military engineering team was assigned to clear and strip a 120-metre-wide right of way to prepare the site for the commencement of the road project.
He explained that the corridor-clearing exercise was scheduled to take 20 weeks, adding that the team had surpassed the halfway mark after just nine weeks of work.
Col. Twumasi expressed confidence that the remaining 86.1 kilometres would be completed within the next 13 weeks, keeping the project on course to meet its target timeline.
The corridor-clearing exercise is regarded as a key preparatory stage, providing the necessary access for contractors before full-scale construction begins.
When completed, the Accra–Kumasi Expressway is expected to transform road transport between Ghana's two largest cities by reducing travel time, improving the movement of goods and passengers, and easing traffic congestion along the existing highway.
Government has identified the project as one of its major transport infrastructure priorities aimed at strengthening national connectivity and supporting economic growth.
Source: Classfmonline.com/Zita Okwang
Trending News

Carbon finance must build Ghana, not enrich consultants — Annoh-Dompreh
15:51
GES describes school malaria campaign as investment in children's future, urges consistent net use
17:16
June 29 downpour among highest daily rainfall recorded since 1995 – Interior Minister
14:58
Ghana Armed Forces deploy troops to flood-hit communities in Accra under ‘Operation Boafo’
11:25
National House of Chiefs urges permanent solution to recurring flooding
14:46
GES stops salary of Bole SHS teacher wanted over alleged misconduct with student
14:04
Bawumia calls for state of emergency over flood crisis
16:44
GRIDCo, ECG temporarily shut down Mallam and Achimota substations over flood risk
11:03
Government to mainstream agroecological practices under Feed Ghana programme
14:43
Prayer must be matched with hard work to build Ghana – Prez. Mahama
13:05